Progress

Following the Construction Contract which entered into force on 30/12/2019, the construction of the GIPL gas interconnection began immediately. We invite you to get acquainted with the progress of this construction work.

JANUARY

On 02/01/2020, the beginning of the construction work was announced. The pipelines' route was marked, a searched for explosives in the pipeline construction area began, archaeological exploration and other works necessary for the start of construction began. For more information.
 
On 13/01/2020, steel pipes from Poland started to be transported to the construction site. For more information.
 
During January:
  • Marked 80 km of pipeline’s route.
  • Transported 14 km of pipes.
  • 5 km of pipes were put along the pipeline’s route.
  • 1 km of pipes were welded.
  • Orders were placed for foreign manufacturers to produce taps, the launching and receiving chambers for the monitoring device and other materials required for the pipeline construction that need more time to manufacture.
FEBRUARY 
 
During the first six weeks of the GIPL gas pipeline construction works, the first kilometres of the pipeline route were welded into filaments. More information.
 
Amber Grid has paid out about EUR 1.3 million in compensation to land owners for GIPL gas pipeline route which will run through the plots of land owned by them. More information
 
The results of the tender for the construction works of the GIPL gas pipeline, in which a pipeline construction company Alvora was the successful tenderer, remain unchanged. A part of the legal action of a company MT Group, who lost the tender for the construction works, whereby the company requested to declare the decision of the Procurement Commission of Amber Grid on the successful tenderer of the tender for the construction works as unlawful, was rejected by the court. More information
 
From the beginning of the works in January to the end of February:
  • 102 km of the route were marked
  • 44 km of pipes were delivered 
  • 28 km of pipes were laid along the route
  • 18 km of piping were welded into filaments
  • 9 km long forest stretch in the GIPL route was cut down 
  • 6.3 km of the welds of the welded gas pipeline were X-rayed. 
 
MARCH
 
After the announcement of the quarantine in Lithuania for the threat of spread of COVID-19 pandemic, the GIPL gas pipeline connection project is being implemented without disruption. Active work with contractors allowed ensuring stable work in all teams. The project is progressing faster than planned – by the end of March, 12% of the entire pipeline construction works were completed. 
 
The planned archaeological research began in parallel with the construction of GIPL gas connection. The historical heritage that has survived into the present day will be explored throughout the territory of 165 km long pipeline route. More information
 
On the occasion of March 11, of the 30th anniversary of the restoration of Lithuania's independence, the Lithuanian tricolour flag with an area of 300 square meters was raised above the gas connection with Western Europe. More information
 
From the beginning of the works in January to the end of March:
  • 68 km of steel pipes were delivered to Lithuania 
  • 54 km of pipes were laid along the route
  • 44 km of piping were welded into filaments
  • 19 km long forest stretch in the GIPL route was cut down
  • 22 km of the welds of the welded gas pipeline were X-rayed
  • 5 km of the route were surveyed for explosives
  • archaeological explorations and detailed research are carried out. 
APRIL
 
In April, the quarantine that is in force in Lithuania due to COVID-19 virus pandemic and operating restrictions did not affect the construction of GIPL gas connection between Lithuania and Poland. Works are progressing as planned and even faster. As planned, the connection will be finished by the end of 2021, and two-thirds of construction works are scheduled to be completed this year. More information
 
The lowering of the welded and inspected parts of piping into the excavated trenches has been started. 
 
The preparation for the most complicated works in this year - horizontal directional drilling (HDD) under the river Neris - is nearing the end.
 
The German partners are scheduled to start work in June. At Kernavė on one side of the river Neris and at Kazokiškės on its other side, work sites are already ready, works of welding of a special pipe, that will be pushed across under the bottom of the river Neris at a depth of 20 meters are nearing the end.
 
From the beginning of the works in January to the end of April:
  • 85 km of pipes were delivered 
  • 71 km of pipes were laid along the route
  • 64 km of piping were welded into filaments
  • trenches were excavated and 6 km of piping were laid
  • 50 km of the welds of the welded gas pipeline were X-rayed
  • archaeological explorations and detailed research were carried out.
MAY
 
The implementation of the GIPL interconnection project is progressing faster than planned. Already implemented 23 percent. of the GIPL project. By the end of May, more than 100 km of steel pipes from 165 km had been delivered to Lithuania.
 
At the request of Amber Grid, the Government granted permission to foreign specialists performing horizontal directional drilling (HDD) work to enter Lithuania. Representatives of the German company LMR Drilling will start the complex construction of the pipeline under the Neris River in June.
 
At the initiative of Lithuanian and Polish gas transmission system operators, independent experts have started preparing a study to assess how to expand the commercial use of the GIPL connection in Europe, and the GIPL gas connection would create maximum economic benefits for Lithuanian, Polish and other European Union consumers. More information
 
From the beginning of the works in January to the end of May:
  • 103 km of pipes were delivered 
  • 87 km of pipes were laid along the route
  • 78 km of piping were welded into filaments
  • trenches were excavated and 17 km of piping were laid
  • buried 14 km of trenches
  • 66 km of the welds of the welded gas pipeline were X-rayed
  • archaeological explorations and detailed research were carried out. 
 
To top